Pavant 3

Pavant 3

The 20 Megawatt (MW) AC Pavant Solar III Project achieved substantial completion in December 2016. The Project is located north of Fillmore Utah, and was constructed by JSI Construction Group, the Engineering, Procurement, and Construction (EPC) Contractor.  The solar project is located north to the Pavant Solar I project and west of the Pavant Solar II project.  JSI interconnected at an interconnection voltage of 46-kV to an existing transmission line owned by Rocky Mountain Power a division of PacifiCorp.  Pavant Solar III LLC owns the facility and will be operated by the JSI O&M Group.

  • Construction Began in June 2016
  • Commercial operation was achieved in December 2016
  • Includes 81,840 modules constructed on the juwi (JES) single axis tracker
  • Project Owner: Pavant Solar III LLC
  • Expected first year generation (avg) 52,500 MWh

 

Pavant 3
25 MWDC
Millard County, Utah
Commissioned in 2016